Start with separate straight wall runs
Enter each wall run separately. The calculator places one stud at each end of every run, then rounds the spaces between them up so the entered on-center limit is not exceeded. Add opening, corner and intersection framing as a separate whole-stud input because those details depend on the wall plan.
Formula and purchase quantities
For each run, stud bays = ceiling(wall length ÷ on-center spacing) and layout studs = bays + 1. Total studs before allowance = layout studs + user-entered extras. Purchase studs = ceiling(total × (1 + allowance)). For plates, each run needs ceiling(run length ÷ stock length) boards per course; the separate run counts are multiplied by plate courses before the allowance is applied.
Three independent checks
A 12 ft run at 16 in on center has ceiling(144÷16)+1 = 10 layout studs; at 24 in it has 7. For 20 ft and 10 ft runs at 16 in, the separate counts are 16 and 9, totaling 25; eight extras and 10% allowance give ceiling(33×1.10) = 37 purchase studs. Those runs need (ceiling(20÷8)+ceiling(10÷8))×3 = 15 base plate boards, or 17 with 10% allowance. A 3.6 m run at 40 cm needs 10 studs and at 60 cm needs 7.
Use the comparison as a material scenario
Plan B shows the quantity effect of a different on-center spacing without declaring either option safe. The DOE/PNNL guidance contrasts traditional 16 in 2×4 framing with 24 in 2×6 advanced framing, but also says local code, high-wind limits, load paths and opening details matter. Match the actual wall assembly, engineering and product requirements.
Assumptions, exclusions and sources
This is a preliminary lumber count, not a structural design or cut optimizer. It excludes headers, sills, cripples, blocking, fire stops, sheathing, fasteners, treated-sill requirements and unusable offcuts. The extra-stud field must reflect the approved drawing. Official basis: DOE/PNNL Building America — Minimum Wall Studs.