METHOD & EXAMPLES
Volume and bag yield are different
Enter finished dimensions and the number of identical sections. Rectangular volume is length × width × thickness; round volume is π × radius² × depth. Add sections of different sizes in separate saved calculations. The result shows cubic metres, cubic feet and cubic yards for the allowance-inclusive requirement.
Worked example: a 4 × 3 m slab
At 0.1 m thickness, volume is 1.2 m³. Adding 10% gives 1.32 m³. An illustrative product yielding 20 L (0.02 m³) per bag requires 66 bags. At 10 per bag, cost is 660. The 20 L starting yield is an example, not a standard for every bag weight or concrete product.
Check the selected product
Use the manufacturer’s mixed yield, not the dry bag weight. Changing the yield unit converts the entered yield. Metres and feet convert dimensions while keeping the physical project unchanged. Allowance is editable and should reflect actual excavation and placement conditions.
Scope of this estimate
This is a material quantity estimate, not a structural design, mix-strength specification or reinforcement plan. Labour, delivery, pump charges, reinforcement and tax are excluded. Confirm required mix and order quantities with the supplier. Reference: QUIKRETE concrete calculators and product yield guidance.
Formula summary
volume = length × width × depth (or π × (diameter / 2)² × depth); bags = ceil(volume × allowance factor / yield per bag)
Updated 27 October 2026. Example prices and yields are illustrative. Calculations run on your device. Saving a result is optional and stores a snapshot locally.
Methods and validation scope